Wind power approvals update: just two remain under old FIT

Orville Walsh of Prince Edward County has updated the list of wind power projects seeking approval under the previous Feed In Tariff program. They are Henvey Inlet (300 megawatts) and North Kent 1 (100 megawatts).

More contracts are to be let for the 2015 Large Renewable Project process, with the announcements now not coming until March 2016. (The original timeline of contract announcements for November-December 2015 was embarrassingly close to the release of the Auditor General’s report which was a scathing criticism of how the Ontario government has handled the electricity file, in particular the rising consumer rates and the losses due to bargain-basement sale of excess power.)

See the current summary here: REA Status Update Dec 23 2015

UK town councils rejected one-third of wind farm proposals

“Increasingly hostile planning environment”

The Independent, December 25, 2015

Councils across the country are now rejecting over a third of all onshore renewable wind projects – often refusing planning permission even when they meet all the necessary statutory requirements.

Official government figures show that in the past year local authorities in England have granted planning permission for just 39 onshore wind projects while rejecting another 23 proposals. Another 17 projects were abandoned during the planning process.

In contrast, over the same period councils in Scotland approved 79 projects while rejecting just over 20.

The figures, released annually, also show that a high proportion of solar-energy farms are being rejected. While the rate

of approval has improved over the past two years, around a quarter of all projects are still being turned down.

Industry figures say privately that they are facing an increasingly hostile planning environment

where local and national politics often trumps fulfilling planning requirements.

They point to rule changes announced after the election that mean wind turbines can only get the go-ahead if they have been backed by local people in neighbourhood plans.

Firms say that the planning process alone can cost them upwards of £100,000 in fees and other related costs.

Ashley Seager, director of the solar energy firm Sun4net, said: “There is no question that it has got tougher to get planning permission … The Tories hate solar and wind because they think it loses them votes to Ukip.”

A spokesman for the Department of Energy and Climate Change said planning decision were a matter for local councils.

A windy Christmas Eve meant more millions in cost to Ontario electricity ratepayers

The day before Christmas

 

T’was the day before Christmas when all through Ontario

the wind was ablowing without great demand

The turbines were spinning and generating power

and some were found to be curtailing in hope

Chiarelli would still pay them and not be considered a dope

The ratepayers were all snuggled in bed

and the Christmas lights were out because of the dread

that would surely come with the hydro bill

and make everything a whole lot worse than a little chill

The children were tucked in bed in winter gear

because their parents were so full of fear

the heat from the furnace would cause the meter to spin

driving up the bill and cause them to send more money to Wynne

The hydro was spilling, the nuclear steamed off,

the gas plants weren’t moving for fear of the racket

that might come to discredit Dalton and others caught sacking

e-mails and records meant to show their defects

and the way they harmed ratepayers and created negative effects

 

Excuse the poetry but it does highlight the mess we found ourselves in on December 24, 2015. To wit:

Ontario’s demand for electricity on December 24th was low based on IESO’s “Daily Market Summary” reaching only 315,336 MWh and “Total Demand” was 385,704 MWh.  The hourly Ontario Energy Price or HOEP market, priced it in a negative way valuing it at -$543,843. What that means is the 72,336 MWh we exported cost Ontario’s ratepayers an extra $102,000 based on the weighted average HOEP price per MWh of -$1.41.  The average cost of production of those exports based on the IESO November average price of $129.53 (net of the DRC) means the 72,336 MWh exported rang up a cost of $9.4 million to be borne by Ontario ratepayers.

That’s not all the costs though! IESO instructed Bruce Nuclear to steam off about 35,000 MWh at an estimated cost of $60.00/MWh or $2.1 million and curtailed 23,500 MWh of wind generation at a cost of around $120.00/MWh adding a further $2.8 million to the day’s costs for ratepayers.

The cost of the exports (negative HOEP of $100 thousand) plus production costs of $9.4 million, steamed off nuclear of $2.1 million and curtailed wind of $2.8 million means just one day cost Ontario’s beleaguered ratepayers $14.4 million without factoring in HST costs.

Premier Kathleen Wynne, her predecessor, Dalton McGuinty, and her Minister of Energy Bob Chiarelli are responsible for delivering those lumps of coal we found in our stockings Christmas morning.

Ho, ho, ho!

(C) Parker Gallant

December 26, 2015

The opinions expressed are those of the author and do not represent Wind Concerns Ontario policy.

Big bucks for Loyalist Twp for wind farm? Or crumbs off the developer’s table?

Loyalist Township

Loyalist Township’s Deputy Mayor is a cheap date

The CKWS Newswatch team reported that “Loyalist Township stands to rake in some big bucks once 26 wind turbines are built on Amherst Island.”

Two key agreements with Windlectric have been authorized by the township related to the 74.3 MW (megawatt) project that will see 26 turbines erected on the island. While the project has been authorized by the Ministry of the Environment and Climate Change (MOECC), the Association to Protect Amherst Island has appealed the approval.  The start date is therefore unknown as the developer must await the ruling of the ERT (Environmental Review Tribunal) which is not expected until the early Spring of 2016.

The term “big bucks” is relative to the size of the project and, perhaps, to the recipient of those “bucks”! In this case the community benefit agreed to is $500,000 annually for the next 20 years. On the surface it sure sounds like big bucks, but the really big bucks will wind up in the pockets of Windlectric’s shareholders.

Here’s how.

If the 74.3 MW capacity development operates at the expected average of 30% of its rated capacity, it should produce almost 2 million megawatt hours (MWh)of electricity and deliver that to Ontario’s grid — whether it’s needed or not. The math is simple:74.3 X 30% X 8760 (hours in a year) = 1,952,604MWh.

We should assume the Windlectric contract was executed prior to the slight downward movement in the feed-in-tariff (FIT) pricing, so for each MWh produced, Windlectric will be paid $135.00/MWh. If you do the math on what their annual revenue will be you might be surprised at the really “big bucks” they will receive!  The gross revenue for Windlectric will be about $26.4 million annually (1,952,604 MWh X $135 = $26,396,010) which most of us would consider “big bucks”!

Loyalist’s ‘big bucks’ is not even 2% of the developer’s revenue

The township will get $500,000 of the $26.4 million which amounts to 1.9% of the takeaway by Windlectic.   If the Amherst Island residents are, as the Deputy Mayor suggested, put “at ease” they shouldn’t be; council should have bargained much harder.

As one resident suggested, the “big bucks” may not be sufficient to even repair the damage to Amherst Island’s infrastructure after construction. And that doesn’t even consider the devaluation1. of property close to the turbines, destruction to migratory birds, plant and animal life, and of course to the 15 to 20 % of people who may feel the effects of the audible and inaudible noise on their health.

What a cheap date!

©Parker Gallant,  December 21, 2015

  1. Property devaluation will lead to reduced assessments and an eventual realty tax loss to the township.

The opinions expressed are those of the author and do not necessarily represent Wind Concerns Ontario policy.

Renew your WCO membership today!

Large crowd smiling

It’s time to renew (or take out!) your membership in Wind Concerns Ontario. Join us as we continue to communicate concerns about industrial-scale, or utility-scale wind power generation projects on the environment, the economy, and human health.

Membership fees are just $15 per person, or $25 for a family of four.

Send a cheque to:

Wind Concerns Ontario

PO Box 509

250 Main Street

Wellington ON  K0K 3L0

OR

Log into your PayPal account

and send your fee to windconcernsONT@gmail.com

For more information, email us at windconcerns@gmail.com

“A major voice” —ReNew Canada

“Wind Concerns Ontario [is] running [a] popular and effective resolution campaign across the province…” Alternatives Journal

Saugeen Shores demands truth from MOECC on UNIFOR wind turbine noise

Documents released via FOI shows hundreds of noise complaints and possibility the turbine exceeds noise regulations

This map, obtained through a Freedom of Information request by Saugeen Shores Turbine Operation Policy (S.T.O.P), indicates the locations of some of the 300 complaints – mainly sleep disturbances – filed in 2013 by residents living near the UNIFOR (formerly CAW) industrial wind turbine in Port Elgin.

Shoreline Beacon, December 18, 2015

SAUGEEN SHORES – 

Because “secrecy breeds mistrust,” Saugeen Shores Coun. John Rich wants “openness and transparency” from officials with the Ministry of Environment (MOE), and UNIFOR (formerly CAW), concerning previously undisclosed noise test results that “appear to reveal” the union’s Port Elgin industrial wind turbine has operated out of compliance with provincial noise regulations.

Through a Freedom of Information (FOI) request, Saugeen Shores Turbine Operation Policy (S.T.O.P) received data detailing 300 complaint-driven observations of noise emissions from the CAW/UNIFOR turbine. The Town’s Notice of Motion said “these observations appear to reveal several incidents where noise emissions from the UNIFOR turbine exceeded the noise standards set by the the MOE.. .which have not been previously disclosed either to the Town of the public at large.” The majority of complaints dealt with sleep disturbance, but also included reports of headaches, nausea, vertigo and other health-related issues.

S.T.O.P spokesman Greg Schmalz brought the information to Council in September at a community forum, and after a review of the data, Saugeen Shores Deputy-Mayor Luke Charbonneau, and Councillors John Rich and Mike Myatt, tabled a Notice of Motion at the Dec. 14 Council meeting to invite CAW/UNIFOR and the MOE to “share and review” the data at a meeting with the Town and S.T.O.P.

Regardless of support or opposition to wind energy, Coun. Rich said “you have to be in support of openness and transparency” by the MOE and CAW/UNIFOR, because “secrecy breeds mistrust.”

“What we want to see is more openness and opportunity for everyone to have discussion. If there is no problem, there is no issue, then things go the way they are. But if there is a problem, then it must be addressed at that time, but I think it’s important that we add a little sunlight to this and make sure we know what’s going on,” Rich said.

Deputy-Mayor Charbonneau said the “real nub” of their Motion is the existence of the FOI documents that “indicate, or at least gives the appearance, that the CAW/UNIFOR turbine has been operating in exceedence [sic] of its noise limits.”

He said that although the MOE required, and CAW/UNIFOR promised, third-party testing to verify turbine operation compliance, it is “concerning” that they have no evidence, and hopes the meeting will get the parties together to determine if the turbine is operating within the provincial guidelines.

Mayor Mike Smith recounted how CAW/UNIFOR had refused a past Town request for the resources to have independent testing done, and said there’s been no contact between the Town and CAW/UNIFOR for several years.

Speaking during the regular open forum prior to the Dec. 14 Council meeting, Schmalz said if the requested meeting occurs, S.T.O.P. will make “simple and reasonable” requests to address the main complaint of sleepless nights by shutting down the turbine from 7 p.m. to 7 a.m.

S.T.O.P also wants the peak daytime noise limit set at 40-decibels, which is the nighttime level for the rest of the province where a 550-metre buffer is required between wind turbines and residences. The setback was not in effect when the CAW/UNIFOR turbine received approval and began operating in April 2013.

Schmalz alleges a “cover-up” by the MOE and CAW/UNIFOR officials who promised “open and transparent” sharing of noise tests, yet S.T.O.P. had to make a FOI application to get the data that showed non-compliance.

“In my books, that’s called cover-up. It leads us to believe that the information that we obtained – which is non-compliant tests – was the norm, and they did not want to have it made public that the turbine was operating out of compliance, and still is, as far as we’re concerned,” Schmalz said, adding S.T.O.P. spent approximately $100,000 for independent noise testing and the FOI request “to get the truth.”

He said they are not asking CAW/UNIFOR to tear down the turbine – the company’s symbol of support for Green Energy and climate change – but don’t want that “mission to interfere with how people enjoy their lives.”

In a Dec. 17 telephone interview, Ken Bondy, UNIFOR’s National Co-ordinator for Health, Safety and Environment, said the claims of non-compliant turbine operations are “unsubstantiated.”

He had a problem with the word “appear” in the Town motion that said the test results “appear to reveal several incidents where noise emissions from the UNIFOR turbine exceeded the noise levels standards set by the MOE…”

“Just because complaints have been filed doesn’t mean the turbine was non-compliant,” Bondy said.

“Is there compliance, or is there not? The only body that would make that determination is the Ministry of Environment, which has now been alleged [to be] in a cover-up operation with the union,” Bondy said, pointing to a 2013 Health Canada study that found there were no harmful effects from turbines, but that “people are annoyed by the sight of them,” Bondy said.

He said, at this point, he is willing to meet with Town and Ministry officials, but not S.T.O.P. officials because of CAW/UNIFOR officials have “concerns meeting with groups that want to portray or publish information that is not factual.”

Officials with the MOE were not immediately available for comment.

 

Loyalist Twp signs Amherst Island road use agreement

CKWS-TV

Community benefit fund no “windfall” says resident Peter Large. “The Township will need that money” to offset construction damage

 

LOYALIST TOWNSHIP STANDS TO RAKE IN SOME BIG BUCKS ONCE 26 WIND TURBINES ARE BUILT ON AMHERST ISLAND. THE TOWNSHIP HAS AUTHORIZED 2 KEY AGREEMENTS WITH THE POWER COMPANY. BUT RESIDENTS ARE CONCERNED THAT COUNCIL’S MOVE WAS PREMATURE — AND HOPING THERE’S STILL A CHANCE TO STOP THE GREEN ENERGY PROJECT. NEWSWATCH’S HEATHER SENORAN HAS THE DETAILS.

PETER LARGE HAS LIVED ON AMHERST ISLAND FOR 15 YEARS.  HE SAYS THE TOWNSHIP’S PLAN TO PUT CLOSE TO 30 WIND TURBINES ON THE ISLAND WOULD RUIN THE EXISTING HERITAGE, BE DANGEROUS TO THE COMMUNITY AND THREATEN WILD LIFE.

“TO HAVE 50 STOREY TALL TURBINES, THRUST INTO THAT COMMUNITY WITHOUT IT’S CONSENT. IT’S JUST NOT RIGHT.”

WINDLECTRIC’S 74.3 MEGAWATT ENERGY PROJECT WAS CONDITIONALLY APPROVED BY THE PROVINCE BACK IN AUGUST.  NOW LOYALIST TOWNSHIP COUNCIL HAS APPROVED A ROAD USE AND COMMUNITY BENEFITS AGREEMENT WITH THE WIND POWER COMPANY.

“With the approval, we now have the framework to proceed with a constructive dialogue with Loyalist regarding the project’s detailed construction planning.”

TO OFFSET THE IMPACT OF THE WINDFARM, WINDLECTRIC WILL GIVE OVER 500 THOUSAND A YEAR.

SOMETHING THE TOWNSHIP’S DEPUTY MAYOR IS HOPING WILL BRING MORE PEOPLE ON SIDE.

“I HOPE IT PUTS RESIDENTS AT EASE. IT CERTAINLY PUTS ME AND I BELIEVE THE TOWNSHIP COUNCIL AT EASE. BECAUSE IT DOES GIVE THE TOWNSHIP AN ELEMENT OF CONTROL. WITHOUT THAT, THERE’S NO ELEMENT OF CONTROL.”

BUT LARGE ISN’T SO SURE.

“THAT COMMUNITY BENEFIT WOULD BE NEEDED TO CLEAN UP THIS PLACE. REPLANT TREES, PUT ROAD SYSTEMS BACK THE WAY THEY SHOULD BE AND SO ONE. YOU CAN’T REALLY CALL IT A COMMUNITY BENEFIT. AMHERST ISLAND WILL NEED IT”

THE AGREEMENT STATES THE TOWNSHIP CAN DO WHATEVER IT WANTS WITH THE MONEY.

“The Benefit Fund can be used by Loyalist Township however it sees fit to benefit its residents.”

TOWNSHIP OFFICIALS ARE STILL WORKING THAT OUT.

“WE’LL WAIT AND FIGURE OUT WHAT TO DO WITH IT, ONCE IT ACTUALLY STARTS FLOWING — IF AND WHEN THE PROJECT GOES FORWARD.”

“THE DEPUTY MAYOR OF LOYALIST TOWNSHIP SAYS, THE EARLIEST THE WIND PROJECT COULD BECOME SHOVEL READY IS THE SPRING OF 2016. BUT WITH NUMEROUS APPEALS STANDING IN THE WAY, HE ADMITS PLANS WILL LIKELY BE STALLED FURTHER.”

THE ASSOCIATION TO PROTECT AMHERST ISLAND LAUNCHED AN APPEAL OF THE PROJECT APPROVAL IN SEPTEMBER BUT THEY DON’T EXPECT TO FIND OUT IF IT’S APPROVED BY THE ENVIRONMENT REVIEW TRIBUNAL UNTIL MARCH OF NEXT YEAR. HEATHER SENORAN CKWS NEWSWATCH, AMHERST ISLAND.

Climate change actions must have proof of effectiveness: municipal group

Giant wind farms: Not doing a thing for the environment
Giant wind farms: Not doing a thing for the environment

MULTI-MUNICIPAL WIND TURBINE WORKING GROUP

MEDIA RELEASE

19 December, 2015

Climate change “solutions” must demonstrate effectiveness

Now that a second Auditor General’s Report has severely criticized Ontario’s electricity system, it is time to rethink a politically motivated energy policy. Action on climate change must not squander crucial time and resources on schemes that may be ineffective, economically unfeasible, or harm human health and the environment.

Why did the Government of Ontario choose to ignore the 2011 Auditor General’s Report that questioned the negligible ability of intermittent wind power to lower carbon emissions because natural gas-fuelled back up is required 24/7?

The Multi-municipal Wind Turbine Working Group, made up of councillors from jurisdictions where wind turbine development has been most intensive, is ideally positioned to observe first hand the effects of wind turbines on the local community. Adverse health effects are occurring to citizens exposed to wind turbines at approved setbacks. Noise and health complaints have been ignored by government officials. Restrictive Environmental Review Tribunal procedures under the Ontario Green Energy Act make residents’ participation meaningless. Biologists’ observations of degradation of significant habitat and loss of biodiversity near wind turbines have been disregarded.

Because of wind power’s difficulty in matching production with demand, a substantial amount of the emission-free electricity from hydro and nuclear plants is being dumped (in order to stabilize the grid) because the Government’s energy policy gives priority to nominally “green” wind energy. This results in throwing away a large portion of the “base load” electricity already paid for by consumers.

Our technical consultant, William Palmer, using IESO (Independent Electricity Supply Operator) data, found that in 2014 hydraulic generating stations (water power) were reduced by 3.2 TWh (Terra Watt Hours) due to surplus base load generation. Bruce Power nuclear units were reduced 588 times, each occurrence resulting in bypassing some 300 MW of electrical equivalent of high pressure steam directly to the turbine generator condensers. These transient adjustments result in accelerated wear on the condensers.

At the same time, much of the excess wind energy has to be sold outside the province at below production cost. This drives down the market price for electricity and means that Ontario is often forced to dump surplus electricity to our neighbours in New York and Michigan at negative prices – paying them to take it, further penalizing Ontario consumers.

The Auditor General’s 2015 report discloses that

  • excess payments to generators over the market price have cost consumers $37 billion between 2006 and 2014
  • are projected to cost another $133 billion from 2015 to 2032
  • electricity consumers will eventually pay a total of $9.2 billion more for renewables under the Min­istry’s guaranteed-price renewable program
  • we are paying double the U.S. average to generators of wind power
  • the electricity portion of hydro bills has risen by 70%.

Not surprisingly the Government has now denied the Auditor General access to Hydro One finances, shielding the company from public scrutiny.

A recently published “Council of Canadian Academies Report: Technology and Policy Options for a Low-emission Energy System in Canada” is an example of policy recommendations that fail to recognize the adverse impact on the existing system that the transition in energy systems is already having. It would have been more useful if its authors had given thoughtful consideration to the IESO data and investigated more fully the consequences of wind turbines in Ontario.

The Multi-municipal Wind Turbine Working Group has written to the Federal Government, which provides substantial subsidies for wind turbines, requesting reality-based climate change policy decisions for solutions that are actually effective in converting to a low emission energy system without themselves resulting in adverse impacts.

CONTACT

Mark Davis, Chair, Multi-municipal Wind Turbine Working Group

mdavis@bmts.com

Res. (519) 353 5466

Wind turbines worry community more than oil pipeline: Financial Post

TransCanada Corp.’s 4,600-kilometre crude oil pipeline proposal aims to connect Hardisty, Alta. to a brand new export terminal in Saint John, N.B., connecting the oilsands to eastern refineries, and crossing hundreds of rural areas such as South Dundas along the route.

The Financial Post, December 14, 2015

BRINSTON, ONT. • Jason Cardinal fiddles with his baseball cap, leans back on the wall and mockingly counts his gripes with the latest energy project imposed on his eastern Ontario township.

“It’s an eyesore, it disturbs their cows, kills their birds and makes whistling sounds, blah, blah, blah,” he deadpans.

Cardinal lives near Brinston, a tiny agricultural community in the municipality of South Dundas roughly 70 kilometres south of Ottawa, where TransCanada Corp. last week hosted an open house for its proposed Energy East crude oil pipeline.

Cardinal and his friends Lloya Sprague and Mike Vanallen are more vocal about the wind turbines installed in the South Dundas municipality than the Energy East proposal. The 30-megawatt South Branch Wind Farm installed by Madrid-based EDP Renewables Canada Ltd., connected to utility distributor Hydro One, is part of Ontario government’s Green Energy Act plan to raise the contribution of renewable sources in the province’s energy mix.

The three firefighters serving the community were at the open house not representing the South Dundas fire department, but “were interested as a person” in the Energy East project, says Sprague.

But it’s not the $12 billion proposal to reverse the existing natural gas pipeline and convert it to take bitumen from Western Canada to East Coast that has Cardinal uneasy.

TransCanada Corp.’s 4,600-kilometre crude oil pipeline proposal aims to connect Hardisty, Alta. to a brand new export terminal in Saint John, N.B., connecting the oilsands to eastern refineries, and crossing hundreds of rural areas such as South Dundas along the route.

FP1212_Brinston_C_JR

The 1.1 million barrels per day project was submitted to the National Energy Board last year, but the Calgary-based company will file an amendment to the application before the end of the year after scrapping plans for a marine terminal in Quebec.

The plan involves repurposing an existing 3,000-kilometre natural gas pipeline that runs from Alberta to Ontario with the Iroquois pump station 12.4 kilometres from Brinston marking the end of that line. As such, most landowners along the line are already familiar with the concept of a fossil fuel conduit running through their backyards.

TransCanada has been holding these open houses across Canada since 2013, as part of it community engagement agenda, but not each event has gone as quietly as Brinston. TransCanada spokesman Tim Duboyce says there have been protests at some of the 116 open houses the company has hosted, while general protests have not been uncommon. In May, hundreds of people marched through Red Head, N.B. to protest the project that ends near that community. Montreal, Kenora and Thunder Bay have also seen protests against the pipeline over the past year.

But it’s hard to find any opposition on this night in Brinston.

Famous for Caldwell towels and Mcintosh apples in nearby Dundela, South Dundas is primarily a town focused on growing soyabean, corn and dairy farming, where residents are more likely to be rattled by solar farms and wind turbines.

South Dundas mayor Evonne Delegrade says she has heard “nothing” on Energy East from her 33 communities that make up the township of roughly 11,000 people. Indeed, the 24 or people who showed up last Monday evening, many with children in tow, were there mostly out of curiosity about, not in opposition to, the pipeline project.

In contrast, Delegrade got an earful from the community last year when 10 wind turbines were installed after approval from the provincial government.

“For the wind turbines, we are not a supporting municipality in that the majority of council did not agree with the Green Energy Act,” Delegrade said, noting that an expansion of the project was voted down by her council.

Once it’s done [with construction], you will never hear about it again

While the Ontario Ministry of Energy is supportive of wind projects, “that’s not happening, to my knowledge, with this (Energy East) project,” Mayor Delegarde says.

Ontarians are paying a price for the Ministry of Energy’s push for wind turbines and solar farm projects, she says. “And this (Energy East) isn’t going to nickel and dime or add any taxes to our residents.”

Indeed, the province has come under sharp criticism for its zeal in pursuing expensive renewable energy projects. In a report this month, the provincial auditor general estimated that the Liberal Government’s decision to ignore its own planning process would cost electricity customers as much as $9.2 billion more for new wind and solar projects.

The wind turbines looming large over the community is part of its problem, says Sprague, noting that in contrast Energy East would be “out of sight, out of mind.”

“Once it’s done [with construction], you will never hear about it again,” says Vanallen.

Dave Chan for National Post
A model of a pipeline construction on display in Brinston, Ont., one of the communities across Canada where TransCanada held information sessions on the Energy East pipeline for local residents.  [Photo Dave Chan]

The latest round of “safety and emergency response days” has taken TransCanada to Prairie cities and towns in Ontario and Quebec. More are planned in Quebec before the end of the year where TransCanada may find a more frosty reception. Unlike much of Ontario, Quebec towns will see new pipes being laid and farmers largely unaccustomed to dealing with pipeline companies. In November, Premier Philippe Couillard sounded an early alarm by noting that the scrapping off the Quebec marine terminal would “complicate” the project’s approval by the province.

To be sure, the criticism is not as vitriolic as it often was during TransCanada’s own Keystone XL pipeline and Enbridge Inc.’s Northern Gateway pipeline campaigns.

Indeed, last year, the Northwestern Ontario Municipalities Association (NOMA), comprising districts of Kenora, Rainy River and Thunder Bay that make up two-third of the province’s land mass, voted in support of the conversion of natural gas pipelines for the Energy East project.

Dave Chan for National Post
South Dundas mayor Evonne Delegarde. [Photo Dave Chan]

“The majority of the community is fine with the conversion as long as the safeguards are put in place,” says David Canfield, mayor of Kenora and president of NOMA.

“But if they were trying to pull a wool over our eyes, as the saying goes, with Energy East, I will be the first one to come down on them,” Canfield adds. “So far they have been very open to our concerns.”

Fearing a repeat of a crude-laden train exploding as happened at Lac Megantic, Que., the municipality association’s largely symbolic vote was driven by a desire to rid the communities of 32,000 petroleum laden rail cars that regularly roll through the towns each year.

“Those tracks don’t bypass the communities — in most cases they go straight through,” said Iain Angus, a member of the Thunder Bay Council and member of NOMA council.

NOMA is also seeking assurances from TransCanada that the communities’ drinking water and hunting and recreational facilities will be protected.

“If things happen that we didn’t like, we would modify our position,” Angus said in a phone interview.

While the umbrella association is in agreement, the city of Thunder Bay, the most populous municipality in Northwestern Ontario, is divided on the project, with mayor Keith Hobbs “totally opposed” to the pipeline. Another council member was not convinced that the pipeline would reduce crude-by-rail traffic.

“At this juncture, [I’m] totally opposed to this pipeline,” Hobbs said in September, according to a CBC report. “Lake Superior, to me, is more important than any jobs. I want jobs in this city, but water comes first. Water is life.”

Dave Chan for National Post
 Local residents of South Dundas look at a map of the region with TransCanada staff at an information session on the Energy East pipeline. [Dave Chan for National Post]

In September, the city council agreed to delay a vote on the pipeline after Angus — who supports Energy East — put forward a motion to defer it.

“The pipeline is 70 kilometres north of the city,” Angus says dryly. “It’s well outside of our municipal boundaries.”

Separately, a volunteer organization headed by Angus has launched an Energy East task force, seeking National Energy Board funding to do its own consultation with First Nations and the general public.

Awareness of the pipeline will likely rise among communities once the the review process gathers momentum, but for now visitors to Matilda Hall in Brinston are merely intrigued passers-by.

One man from Morrisburg, with a worn-out cap taming his long, graying hair, brought his three young daughters to the event. After spending about 20 minutes in the hall, he stepped out of the centre and lit a cigarette that he had rifled from a small ziploc bag.

A TransCanada employee started explaining the company’s spill response, and the man punctuated his response with a slightly bored “Is that right?” line. Did he get all his concerns addressed, he is asked. He sucks on his cigarette: “Yeah, I wasn’t concerned, just curious.”

yhussain@nationalpost.com
YAD_FPEnergy

 

Wind Concerns Ontario note: the Financial Post photographer had to work hard to get a pic of Brinston without a turbine in it. Here is a photo from Ottawa photographer Ray Pilon of a house and a 3-MW turbine, at Brinston.

3-MW wind turbine and house near Brinston: Ontario hasn't learned a thing. [Photo: Ray Pilon, Ottawa]
3-MW wind turbine and house near Brinston. [Photo: Ray Pilon, Ottawa]

White Pines appeal schedule announced

The remaining dates for the White Pines appeal in Prince Edward County was announced at the hearing in Toronto yesterday, December 15.

  1. Final submission scheduled for January 5th.
  2. Responding submission scheduled for January 15th.
  3. Reply January 19th
  4. Oral submission January 20th
The Tribunal also decided to allow themselves additional time to write the decision.  They have adjourned the hearing to allow for an extension of the deadline from January 29 2016 to Feb. 19, 2016.
For more information on the power project and to donate to this legal action please go to the website for the Alliance to Protect Prince Edward County.