Enercon turbine shreds in Germany

Shredded blades on Enercon turbine [Photo Gudrun Ponta/EDR]
March 12, 2018

Eder Dampf Radio in Germany is reporting a spectacular incident in which the rotor blades of an Enercon wind turbine shredded, and threw fiberglass particles over a half-kilometer.

The report follows (translated using Google Translate):

Borchen / Paderborn (Gudrun Ponta / nh). 

Two rotors of a new ENERCON E-115 wind power plant in the district of Paderborn are torn to pieces and cause extensive contamination with innumerable sharp-edged glass fiber particles.

At 7pm on March 8th, two rotors of a brand-new ENERCON E-115 wind turbine were completely torn apart – the parts flew over 500m.

Neither builder ENERCON nor operator WestfalenWind have informed the public or the police after the incident, although there was danger to their lives due to flying debris. After an Ettelner citizen informed the police, the area around the damaged wind energy plant was cordoned off on a large scale.

The barriers of the accident site reached almost to Etteln . On March 6, the wings were mounted, the system was not connected to the mains. Obviously [it] overrun and the wings could not be stopped. It is said that the wings only turned at 19 km / h when they were torn to pieces.

ENERCON / WestfalenWind play down the incident – the rotors were merely “broken off” and dropped directly to the ground, it was said in first reports – how can it be that parts have flown over 500m? It is just a lucky coincidence that no one was injured in this spectacular accident of a brand new wind energy plant in Borchen-Etteln.

This latest incident again raises concerns about safety around wind turbines, particularly where turbines are located close to highways, as in Chatham-Kent-Essex.

UPDATE: Windpower Monthly has a newer version of the story, which may be found here. The wind industry publication notes that an anti-wind power citizens’ group has posted photos of the turbine failure, and claimed debris spread 800 metres—in fact, the group said 500 metres.



Prince Edward County citizens ask Enviro Commissioner for review of White Pines environmental impact

Blandings turtles: still in danger [CBC photo]
March 12, 2018

The Alliance to Protect Prince Edward County (Wind Concerns Ontario community group member APPEC) and the Prince Edward County Field Naturalists (PECFN) submitted a Joint Part IV Application to the Environmental Commissioner’s Office (ECO), regarding the White Pines wind power project.

The power project has faced numerous appeals and legal actions over the years, and has been reduced from 29 turbines to 27, and is now at nine. The community had thought that the reduced capacity would result in cancellation of the contract with the Independent Electricity System Operator (IESO) but the IESO simply cut a new contract for the power developer.

Concerns about environmental impact remain, however.

“Basically, we are asking the ECO to conduct a formal review based on the concerns and evidence we have provided relating to the Blanding’s turtle, the Little brown bat and migratory birds,” says APPEC Chair Gordon Gibbins.

“It was important for us to submit the Part IV Application before going forward with any appeal to the Divisional Court.  Our Application sets this process in motion, and in fact includes almost all the same issues we had planned to raise at the ERT hearing before our appeal was dismissed,” Gibbins explains.

“The ECO has everything it needs to make a decision on whether or not to conduct a review.   We’ve been told that the ECO will forward this evidence to the MOECC and to the MNRF (Ministry of Natural Resources and Forestry) as well as make their own conclusions.”

The White Pines project has also been fraught with accusations of violations of its Renewable Energy Approval, as the power developer engaged in land clearing and road use outside of signed agreements.

For more information, go to: https://appec.wordpress.com/




Infrasound chamber developed at U Waterloo

A team has created a special chamber in which infrasound can be produced, in the hopes of aiding accredited health researchers.

March 12, 2018

Richard Mann, assistant professor on Computer Science at the University of Waterloo, has informed Wind Concerns Ontario of a new development:

“We have successfully produced infrasound, as a mirror of that produced by Industrial Wind Turbines, in a chamber capable of accommodating a human test subject. This will permit others, with appropriate medical training and ethical oversight, to research the effects of infrasound on humans.”

In a PDF document with details on the project, he provides the rationale.

A significant number of people, who live in proximity to Industrial Wind Turbines, complain about a variety of physical and emotional symptoms. They believe these symptoms are caused by Infrasound produced by these Turbines. Some of these symptoms include, but are not limited to, nausea, tinnitus, sleep deprivation,

vertigo, high blood pressure, depression, anxiety, and other ailments, which to them, have a profound impact on quality of life.

Sadly, both the wind industry, and governments, have not responded to these concerns in any meaningful way, and those affected are given little if any support.

Some have actually had to leave their homes and have endured financial distress as a result.

Countless others continue to suffer with little hope for relief. To profoundly add to their distress, many are met with the inference that these problems are “all

in their head (Crichton et al, 2014; Chapman 2015).

“There is a genuine need to study human thresholds and/or response to infrasound exposure systematically and reliably in a lab setting,” Mann says.

“Our motivation for this project was based on the need for tools, to allow others with appropriate medical training and ethics approval, to move forward with this research.”


Read the document here: https://cs.uwaterloo.ca/sites/ca.computer-science/files/uploads/files/cs-2018-01.pdf

Unifor turbine not compliant: MOECC

Noise abatement plan to be in place by March 18

Unifor turbine: Years of procrastination and failure of the regulator to regulate

March 5, 2018

Owen Sound District Manager for the Ontario Ministry of the Environment and Climate Change Rick Chappell told West Grey Council and a packed room of citizens today that the controversial single wind turbine in Port Elgin owned and operated by Unifor, is not compliant with provincial noise regulations.

A noise abatement plan has been ordered by the Ministry and must be in place by March 18.

The Unifor turbine has resulted in hundreds of complaints of excessive noise over the years, several TV news stories, and statements from the local municipality to the effect that the MOECC is failing in its role as a regulator.

West Grey Council, which had asked Chappell to appear to answer questions about why wind turbine noise complaints were not being resolved, accepted the news, and one councilor demanded that the MOECC now personally call everyone who had filed a report, and give them the news.

Councillors remarked that the decision to test the Unifor wind turbine noise output was the result of citizen complaints; a councilor advised residents to “keep complaining.”

Wind Concerns Ontario has reports provided by the MOECC that show 236 reports were filed up to the end of 2014. In the years 2009-2014, over half of the noise reports received by the MOECC got no response.


Wind turbine construction destruction: “the rules are just made to be broken”

March 5, 2018

Roads blocked without notice on Amherst Island: breaking all the rules and getting away with it (Photo: Brian Little)

“All the rules are made to be broken”

Representatives of three community groups where wind turbine projects are currently under construction, addressed the Wind Concerns Ontario conference in Kingston this past weekend, and told hair-raising stories of violations of Renewable Energy Approvals, disobedience of municipal orders, ignoring conditions of road use agreements, and more.

Anne Dumbrille, chair of the County Coalition for Safe Appropriate Green Energy (CCSAGE-Naturally Green) and Orville Walsh of the Alliance to Protect Prince Edward County (APPEC), both based in Prince Edward County, detailed the abuses of the Renewable Energy Approval and IESO contract by Germany-based wind power developer wpd in construction of the contentious White Pines wind power project.

The White Pines project was originally planned to produce electricity for Ontario’s surplus-laden power grid via 29 huge wind turbines. A successful appeal based on heritage aspects of The County reduced the turbine number to 27; another appeal (Hirsch v. MOECC) was partially successful and saw the project reduced from 27 to 9 turbines, based on harm to endangered species.

“We had been operating under the belief that having to meet the 75 percent of power requirement in the contract with the IESO [Independent Electricity System Operator] actually meant something,” said Walsh. “It turns out, it doesn’t. Contracts don’t mean anything — they can do whatever they want.”

Dumbrille echoed that with a litany of abuses. The White Pines project is way past its specified commercial operation date, she said, which should mean the IESO could terminate the contract, but it hasn’t. “The Long Stop Date has no meaning or relevance, despite being in the regulations,” she said. “The decision appears to be political.”

The public also expected that while the power project was being appealed, construction work would not be allowed, particularly in the areas presented as habitat for the endangered Blandings turtle, but in fact, both the MOECC and the Ministry of Natural Resources and Forestry allowed it. Only when citizens took action in court was a stop work order achieved.

“Why must citizen groups rather than government protect habitat destruction?” Dumbrille asked.

The land clearing in turtle habitat continued after the appeal for the nine remaining turbines outside the limits imposed by the Environmental Review Tribunal. Again, citizens went to court, and again a stop order was issued, but not before habitat was destroyed. A transmission station is planned to be built in a stream bed which is against regulations and will require the taking of water. Again, the MOECC appears to side with the power developer on all issues.

“All the rules are made to be broken,” said Dumbrille, “to benefit the wind power developer. And the public has no right to information, apparently.”

Janet Grace, past chair of the Association to Protect Amherst Island (APAI), described numerous violations of the Renewable Energy Approval, road use agreements, and provincial safety regulations by “Windlectric” a shell company developing a power project on the island for Algonquin Power. Construction staff and vehicles are supposed to be using a barge to get to the island, she said, but they’re not: instead, they use the passenger ferry which is resulting in delays for Island residents, many of whom work across the water in KIngston, and concerns about safety.

Roads are blocked without notice, and construction throughout the winter has virtually destroyed roads, so much so that the municipality Loyalist Township issued a stop work order. Resident photographs indicate however, that the order was ignored, with the power developer construction firm continuing work. In addition, Grace said, the company is supposed to stop work at 7 PM, but in reality is working until 11 PM.

“The sad thing is, Grace said, “we know this is just the beginning of what is being done to our Island. There are rules being broken, and violations … the MOECC gives them exemptions. They’re just getting away with it all.”


Surplus wind power costs millions: Parker Gallant

March 5, 2018

Parker Gallant : hydro and nuclear could have done the job and saved millions mismanagement. [Photo: Metroland Media]
Being asked to do a presentation at Wind Concerns Ontario’s annual conference this past Saturday, to describe the costs associated with industrial wind turbines was something I relished!

The presentation I developed used IESO information for 2017.

Discovered in the preparation of my presentation was the fact that that nuclear and hydro power alone could have supplied over 100% of all grid-connected consumption for 2017, at a average cost of about 5.9 cents per kilowatt hour.

The cost for Class B ratepayers in 2017 however, was almost double, coming in at 11.55 cents per kwh.

So why the big jump? Have a look at the presentation to see why and look at Slide 6 in particular where you get an inkling of how IESO view the reliability of industrial wind generation in their forward planning process!

PresentationParkerPPT final

(Reprinted with permission from Parker Gallant Energy Perspectives)

Australian court: wind turbine noise a “plausible pathway” to disease

Court finds an established association between annoyance (used as a medical term) and some diseases that result from prolonged stress

Pathway to Disease: Australian court links wind turbine noise with possible diseases
Hamilton Spectator
Natalie McGregor
15 February 2018

In a World first, Australia’s Administrative Appeals Tribunal (AAT) has declared that the “noise annoyance” caused by wind turbine generated low-frequency noise and infrasound “is a plausible pathway to disease”.

At the AAT hearing in Adelaide, the impacts of wind farm noise were considered by a senior Federal Court judge; the most thorough medial and scientific inquiry on the subject matter conducted in Australia to date.

The Tribunal’s findings were based on the “established association between noise annoyance and some diseases, including hypertension and cardiovascular disease, possibly mediated in part by disturbed sleep and/or psychological stress/distress”.

In its summary, and with unanimous support from relevant experts, AAT found that there were numerous recorded instances of wind turbine noise exceeding 40 dB(A) — a recognised threshold for annoyance/sleep disturbance.

“Even if it is not audible, low-frequency noise and infrasound may have other effects on the human body, which are not mediated by hearing but also not fully understood,” the summary reads.

“Those effects may include motion-sickness-like symptoms, vertigo, and tinnitus -like symptoms.”

It was also established that the current method adopted by windfarms to measure noise — the dB(A) scale was not suitable for the task, because a significant proportion of sound emitted by wind turbines is in the lower frequency range, where the scale cannot accurately identify the presence of frequencies or the peaks and troughs of their occurrence.

Instead, the dB(A) scale averages out the sound levels, masking the occurrence that could be causing harmful health side-effects.

The dB(A) weighting system is the basis of every wind turbine noise guideline in operation throughout the world.

With majority support from relevant experts, the Tribunal found that the most accurate way of determining the level and type of sound present at a particular location is to measure the sound at that location.

In conclusion, AAT noted the World Health Organisation stance that there is “sufficient evidence from large-scale epidemiological studies linking the populations exposure to environmental noise with adverse health effects”.

A Moyne shire resident living next to the MacArthur windfarm outlined the health impacts she has experienced since the wind farms were established.

“Severe ear pressure and pain, it’s actually in the inner ear; head pressure and headaches; my heart goes bananas, my whole body burns, and I feel sick,” she said.

“And (the symptoms) just come back immediately when in direct proximity to low-frequency emissions, it can happen anywhere, and it’s not just mild, it’s really debilitating.”

AGL started the consultation process with the community surrounding the proposed Willatook windfarm, raising concerns from residents about the proliferation of turbines in the area.

Community members met with South West Coast MP Roma Britnell over the weekend to voice concerns.

“Really (the meeting) centred around the fact that they will be surrounded, some of them, by the wind farms,” Ms Britnell said.

“They felt that it was a cluster effect and that it was unfair, that just because the power line goes through one area, they shouldn’t have to be the ones to had to take all the load of the 220-metre from tip- two-base structures in their backyard.”

Ms Britnell expressed no strong opinion in favour or against wind energy, simply saying we need to “get it right”.

“I am all for getting the renewable energy balance right, and wind is part of the solution, but wind is not the answer where there is no ability to store it,” Ms Britnell said.

“I’m afraid I still can’t meet the demand for supply when I want to milk my cows or have my shower when the wind isn’t blowing.

“Wind is not meeting the baseload and the biggest restriction I hear from community members is the supply issue, and that’s what the government is really not addressing.”

Tony Edney, director of the water foundation — an advocacy group for properly conducted, multidisciplinary research into health problems reported by people living in the vicinity of wind turbines and other industrial uses — told the Spectator that not every windfarm would necessarily generate problems.

“The location, topography, layout and design of the installation of factors that combine with climactic conditions to produce sound generating profiles of potential harm for some receiver sites,” Mr Edney said.

“And not everyone is adversely affected by wind farm noise. It is in part a matter of individual sensitivity or propensity, think of seasickness, and how we are not impacted equally by that malaise.”

Mr Edney said it was “simply no longer possible” for the industry to say that its technology was “clean, green and completely harmless”.

“Country people deserve to know what exactly they are dealing with when talk starts up about our windfarm proposed for their district,” Mr Edney said.
Hamilton Spectator

Quebec court: municipalities must protect citizens’ water

A municipality fighting back against a corporation has won its defence of a lawsuit, and its rights to defend citizens’ water has been upheld. The Precautionary Principle must be applied. This case will be important to Chatham-Kent area residents whose wells have failed during wind turbine construction activity.

March 1

Gastem continued Restigouche Southeast for $ 1 million to have adopted a regulation prohibiting drilling within 2 km of the sources of drinking water.

Oil and gas developer Gastem sued municipality Ristigouche-Partie-Sud-Est for $ 1 million for adopting a regulation prohibiting all drilling within 2 km of its drinking water sources. Photo: Radio-Canada

From ICI Radio Canada

Restigouche-South-East: Gastem dismissed


The Superior Court dismissed the motion of Gastem, which sued the Municipality of Ristigouche-Partie-Sud-Est for $ 1 million.

A text by Joane Bérubé with the collaboration of Sylvie Aubut and Ariane Perron-Langlois

The oil and gas exploration company claimed that the municipal by-law protecting drinking water had forced it to stop its exploration activities in the area.

In her decision, Justice Nicole Tremblay states that the by-law “is the result of serious work” and that “Restigouche must ensure the protection of watercourses in accordance with government rules”.

The judge ordered Gastem to pay Restigouche-Partie-Sud-Est $ 154,000 within 30 days of the decision.

The company will also have to pay $ 10,000 for part of the costs incurred by the Municipality to defend itself. The trial took place in September in New Carlisle, Gaspésie.

A relieved municipality

Restigouche-Part-Southeast welcomes with relief the decision of the court. For four years, the small municipality of 157 inhabitants tried to raise funds to finance his defense against Gastem. The Restigouche Solidarity campaign raised more than $ 340,000.

“Today, we raise our glass of drinking water to the health of Quebec’s water and to all those who supported us! “Said the mayor of Restigouche-Part-South-East, François Boulay.

According to Mayor Boulay, the bill for the expenses incurred by the Municipality amounts to $ 370,000.

The money that Gastem has to pay will be welcome. Should Gastem waive its recourse rights, the surpluses will be transferred to another case for drinking water in Quebec, says Mayor Boulay.

The Municipality, however, prefers to wait to hear Gastem’s decision on his right of appeal before disposing of it.

François Boulay, Mayor of Ristigouche-Partie-Sud-Est.

François Boulay, Mayor of Ristigouche-Partie-Sud-Est Photo: Radio-Canada

The case was very important for other municipalities, since it involved their power to legislate to protect drinking water. The judgment also contains several references to the duty of municipalities to protect the environment and the duty to subscribe to the precautionary principle.

Gastem’s reaction

Raymond Savoie, president of Gastem, says he is disappointed with the judgment. “We read the document, we try to understand; for the moment we are there, “says Savoie, who refuses for the moment to comment on the decision.

Mr. Savoie does not rule out the possibility that the company can appeal the decision, but prefers to wait for a more detailed analysis of the judgment.

In the region, Sylvain Roy, MNA for Bonaventure, is pleased with the verdict.

Impacts on other municipalities?

The deputy Roy believes that this is a “great victory for democracy and territorial sovereignty”. Mr. Roy hopes the decision will serve as case law for similar cases.

The lawyer of the Municipality, Jean-François Girard, is not surprised at the amounts that will pay Gastem in Restigouche-Part-Southeast. “We had,” he said, “very carefully pleaded the abusive nature of the appeal and the fact that it was up to Gastem to reimburse us for these costs. ”

The fact that the court recognizes this element of law is also very important, according to Mr. Girard. “It will force companies who want to sue municipalities to think twice if it is not legally sound,” he says.

For the lawyer, the victory is indeed that of a small municipality struggling with a pursuit that had no other purpose than to be punitive. “You have to think about it, there are 84 taxpayers in Restigouche! Says Girard.

The latter also sees the victory of the municipal world. “This judgment,” he adds, “recognizes the role of municipalities and the fact that municipalities can take up the cause according to the interest of their citizens, interest in the health and well-being of their population. . ”

Mayor Boulay also believes that the judgment brings very important elements on the municipal competences in environmental matters.

The president of the Quebec Federation of Municipalities (FQM), Jacques Demers, also welcomes the fact that the judgment reaffirms the municipal powers and their duty to intervene in the protection of the environment. “However, we must not forget that these powers must be exercised in compliance with the legislative framework in force,” says Demers.