Wind wasted again — millions spent on unneeded power last weekend

October 16, 2017

Wind turbines near SS Marie: power not needed but cost us millions (National Post photo)

October 15, 2017 was quite a windy Sunday.   Being a mild fall day too, that meant Ontario’s demand for electricity was low according to the IESO’s Daily Market Summary.  Total Ontario demand was only 313,000 MWh for the whole day.

Unfortunately for ratepayers, it was a beyond the norm windy day — industrial wind turbines spread throughout the province were spinning well beyond their yearly average of 29/30% of capacity.

According to the IESO’s daily generator report, the wind turbines could have supplied almost 84,000 MWh* of power, or about 27% of all the power consumed by Ontario’s ratepayers (approximately 83% of their capacity).  As it turned out, IESO curtailed or did not accept 42,500 MWh for which wind developers were paid $120/MWh anyway, and the 41,200 MWh grid-accepted power generation got them the standard $135/MWh.

What the foregoing means is wind developers were paid approximately $10,660,000 for curtailed wind generation and grid-accepted power.  That works out to a cost per MWh of $260 or 26 cents a kilowatt hour — almost double the current generation cost, for which 25% is being refinanced under the Fair Hydro Act.

As it turned out, the grid-accepted wind generation really wasn’t needed: as the IESO “Summary” report indicates, Ontario’s net exports averaged 2,110MW per hour or 50,640 MW at a negative price of $0.99. That means Ontario’s ratepayers picked up another $50K to provide our neighbours (principally Michigan and New York) with cheap power.

No doubt Ontario was also spilling hydro and steaming off Bruce Nuclear which ratepayers were also paying for on that windy October Sunday.

More proof that wind power provides costly, intermittent and unneeded power. More proof that the Green Energy and Economy Act should be tossed out!

 

 

*All numbers are rounded.

Ontario government abdicated role as environmental protector: WCO

“The Green Energy Act was the biggest con ever in Ontario” — MPP Todd Smith

Hundreds marched in Picton on October 15th. The Green Energy Act “the biggest con, ever.” [Photo Wind Concerns Ontario]
October 16, 2017

Hundreds of community members in Prince Edward County marched down Picton Main Street yesterday to protest the “White PInes” wind power project, and the Ontario government’s wind power policy. The march was followed by a three-hour information session.

The project by Germany-based wpd was trimmed from 29 to 9 turbines in various appeals, but the developer is still proceeding despite questions as to whether it actually has a contract with the Ontario government, and whether the 9-turbine project makes any financial sense.

Among the speakers at the information session was Wind Concerns Ontario president Jane Wilson, who reviewed the findings of the organization’s request for documents on reports of excessive wind turbine noise made to the Ministry of the Environment and Climate Change, under the Freedom of Information and Privacy Act.

“We wondered, what happens to all the reports being made to the government? Here’s what we learned: The government does nothing,” Wilson said.

“This government has completely abdicated its role as a protector of the environment and people. Instead of functioning as a regulator, it is now a facilitator for huge multi-national corporations whose last concern is any benefit to the environment.”

Everybody knows there are health effects

Dr Robert McMurtry said adverse health effects related to wind turbine noise emissions, including inaudible noise and low-frequency noise, are disturbing, especially because both government and industry deny them. “Everyone’s pretending the emperor has clothes,” said Dr McMurtry, a member of the Order of Canada and a former Dean of Medicine. “There are adverse health effects and everybody knows it — that’s why we have setbacks in the first place.”

Other community members spoke on concerns for wildlife, heritage features (the nine turbines will surround the historic Loyalist settlement of Milford), and the effect on citizens’ water wells. While the power developer claimed there would be no problems as a result of sinking huge wind turbine foundations into the ground, which features fragile karst topography, Les Stanfield remarked that there are sinkholes all over the County, and there were concerns about the turbines’ effect on aquifers.

MPP Todd Smith said loudly, what no one had said was that the whole push for wind power and the Green Energy Act was “the biggest con job” ever in Ontario.” Obviously, he said, repealing the controversial act is mandatory.

Renowned vintner Norman Hardie said the power project “must not go ahead.” Eco-tourism, the County’s economy, and the entire character of the area would be irreparably damaged, he said.

Power not needed

The last speaker was Prince Edward County Mayor Robert Quaiff who said that the project must not proceed, and nothing less than 100-percent success in stopping it was acceptable. He questioned the contract with the IESO, and the feasibility of the project. “I can’t understand why [wpd] is doing this? Are they punishing our community for daring to oppose them?”

Wilson added to her presentation that at the time of the event, wind power was being constrained or held back at record levels in Ontario, according to IESO data for Sunday.

“That just adds insult to injury,” she said.

Residents last week filed notice of legal action against the Independent Electricity Systems Operator or IESO over the project, which they say has no legal contract. The first court date is November 17 in Picton. Donations accepted at the community group website.

More stories here.

Belleville Intelligencer

County Live

Quinte News

 

“Gasping in despair”: Ontario’s rural communities, victims of Wynne government wind power cabal

In aiding wind power corporations, the Ontario government has essentially released wild dogs onto Ontario’s landscape without oversight, or means of bringing them to heel

“To despoil the environment. To slaughter endangered species. To make folks sick.” From the independent Wellington Times, a powerful overview of what the McGuinty-Wynne governments have done to Ontario while aiding huge corporations to build wind power plants

 

Ontario gothic

Posted: October 6, 2017 at 9:03 am   /   by   /   comments (4)

It begs the question: what was Kathleen Wynne and her government smoking when they let loose their own man-made monsters across rural Ontario—in the form of industrial wind developers and speculators?

Even if you buy the sentiment that their motivations were well-intentioned, the undeniable outcome of the Green Energy Act is that Kathleen Wynne and Dalton McGuinty have spawned armies of amoral monstrous corporate creatures and have let them loose to roam unfettered across the province. To wreak havoc in rural communities. To despoil the environment. To slaughter endangered species. To make folks sick.

Worse, our government has paved the way, clearing hurdles and slashing regulations to enable these creatures to prey upon vulnerable communities, natural habitats and endangered species. Now they have lost control of their grotesque creations. Even Kathleen Wynne must know how this story ends.

Near Chatham, folks believe the wind developer working nearby has poisoned their wells—allowing toxins into their drinking supply. They have done the testing. They have spoken out. They have protested. Marched on Queen’s Park. Kathleen Wynne has ignored them.

Wynne, her government and her supporters comfort themselves believing the scourge they have unleashed—though ugly and abusive— is a necessary evil. That the greater good is being served. They ignore the folks holding up jars of black liquid, pleading with the province to test their water, drawn from wells that have become undrinkable since the wind developer began driving piles into the bedrock to secure its massive wind turbines. Even Chatham- Kent’s mayor has demanded Kathleen Wynne intervene to protect these residents. It has made no difference.

Left without the protection of the province—without the safeguards that would protect them from any other development— these folks took matters into their own hands. In August, they began blockading the construction site— neighbours joining together to form a line against the threat to their drinking water.

On Monday, in a cruel blow, the developers— a Korean conglomerate and its American partner—won a court injunction barring any further blockades of the project. The judge said he wasn’t trying to muzzle opponents, but to “prohibit unlawful acts”.

People have to prove their water has been poisoned

In Ontario’s perverse hunger for industrial wind turbines, it turns out Chatham-Kent residents must first prove they have been poisoned by the developer, before they may seek justice. By then, of course, the damage will have been done. Recourse will expensive and, for most, unattainable.

Four years ago, the giant American wind developer Next Era sued Esther Wrightman for defamation. On her website she had altered the company’s logo to NextError and Next Terror. They wanted the logos removed or they would litigate the mother of two young children into oblivion. All these years later, the legal action is still pending. Wrightman wakes up every morning with the weight of this action still weighing on her head.

In Prince Edward County, a wind developer has been barred from constructing a nine-turbine project near Milford between May 1 and October 15. This was done expressly to protect the nesting grounds and habitat of the Blanding’s turtle, an endangered species in the province.

Nevertheless, crews have been busy these past few weeks clearing vegetation, preparing the site and delivering heavy equipment onto these protected lands. There are no consequences for ignoring the rules.

Families have left homes–no one will help

So, a developer ruins drinking water without penalty, another bullies a young mother into silence, and yet another crushes rules meant to save an endangered species. This is our Ontario. There are dozens more distressing stories just like these. Too many sad accounts of families forced to leave their homes because the noise and vibration from the massive machines proved intolerable.

No one is coming to help the folks in Chatham-Kent. No one from our government—those we entrust to protect us—is intervening between Next Era (market capitalization of $68 billion) and Esther Wrightman. And no one is coming to protect endangered species in South Marysburgh.

Wynne has lost control of her destructive and unscrupulous brutes. When the Liberal government eliminated the safeguards that once protected us from these threats, and cut municipalities and communities out of decision-making, they may have believed they were just streamlining processes. Instead, they unleashed wild dogs onto the Ontario landscape without oversight or the means to bring them back to heel.

Untethered by moral, ethical or community concerns, these corporate beasts consume and ravage everything they can get away with. Folks who have fought for years to protect the things our government was supposed to safeguard, have been left gasping in despair. Lacking legal remedies or protection, some have begun considering other means to protect their families, their communities and their land. If the government won’t protect them, they will do it themselves.

This is the horror Kathleen Wynne and Dalton McGuinty have wrought.

 

rick@wellingtontimes.ca

 

Something ‘not right’ with Ontario government push for wind power

Wynne government “moves the goalposts,” bends the rules to get wind power through … and nobody knows why, says prominent Prince Edward County businessman

The Wynne government ignores economic, environmental and health reasons to cancel wind power, but pushes forward anyway: why? “Back-handed deals,” says a businessman

October 3, 2017

One of the questions Wind Concerns Ontario routinely gets from the media, after we’ve detailed the lack of environmental benefit from industrial-scale wind power developments, the harm being done to the environment, and the physical harm being done by exposure to the noise emissions from wind turbines to some people, is WHY does the government persist in this policy, in the face of all the evidence — even just the questions — about it?

WHY, when the government admits it has a surplus of power (and is selling off wind power at a loss to other jurisdictions) is it continuing to sign contracts and grant approvals for new projects?

WHY, when the Minister of Energy has admitted there are problems and “sub-optimal siting” does the government have plans to inflict unwanted and unneeded wind power projects on more Ontario communities like Otter Creek, The Nation, North Stormont and Dutton Dunwich?

Our answer has been, there is something else going on here, agreements that have been made, contracts signed that we may never know about, that prevents the Ontario government from responding rationally.

That thought was echoed yesterday in an interview Jerry Agar of CFRB 1010 did with Norm Hardie, owner of the renowned Norman Hardie Wines in Prince Edward County.

On the sensible side, Hardie says in his interview, the government could pay $500,000 to get out of the White PInes contract and save $100 million in costs to electricity consumers … but it won’t. They know all the objections, Hardie says, but he can’t help but feeling “there is a back-handed deal …there is something creepy going on we will probably never know about … something is not right.”

Despite the money being lost, the damage to the environment, community and potentially to the local community in Prince Edward County for example, Hardie says, “they are intent on destroying us.”

Wind power: nowhere to be seen during Ontario heat wave

In fact, wind power generators probably used more power than they produced, says Parker Gallant.

Big Wind says “the wind is always blowing somewhere!” Except when it’s not. Exactly when it’s needed, not there.

Parker Gallant Energy Perspectives

September 26, 2017

The impact of the well above normal temperatures Ontario has been experiencing for the past several days in September was seen in hour 17 (5 pm) yesterday, September 25, 2017.

From all appearances, hour 17 set the record for high peak demand in the province for the current year as businesses and homes had air conditioners and fans blasting away, drawing power from the grid.

Peak demand for hour 17 was 21,639 MWh.

Nuclear and hydro along with gas generated 20,091 MWh during that 60 minutes and was supplemented by net imports of 1,221 MWh from Manitoba and Quebec.

Where were “renewables” (excluding hydro), wind, solar and biomass? Together, they generated a miserly 307 MWh. In fact, wind power generators probably consumed more then they contributed with a minuscule 67 MWh. That 67 MWh represented about 1.5% of their grid connected capacity of 4,213 MW.

Put another way, wind power contributed .3% of peak demand!

All this simply proves industrial wind turbines (IWT) are unreliable and intermittent. If they can’t be counted on when we need the power, why does our Minister of Energy Glenn Thibeault and Premier Wynne continue to support them? Why not cancel contracts for wind power plants that have not commenced construction?

The time has come for the Ontario Liberal government to admit that industrial-scale wind turbines deliver nothing more than unreliable, intermittent power that must be backed up with reliable power in the form of nuclear, hydro and gas.

The dream is over.

(C) Parker Gallant

Ontario a world leader in wasted wind power

Scottish electricity customers are upset that they are paying millions to wind power producers not to produce — Parker Gallant says Ontario has that beat … by a long shot.

Here’s his latest on how Ontario pays millions (added to our electricity bills) to wind power producers, because wind power is produced when it’s not needed.

Samsung Belle River project racing for completion: Ontario doesn’t need more wind power

And the winner (loser) is … Ontario

A recent article appearing in Energy Voice was all about the costs of “constraint” payments to onshore industrial wind developments in Scotland.  It started with the following bad news:

“According to figures received by Energy Voice, the cost of paying wind farm operators to power down in order to prevent the generation of excess energy is stacking up with more than £300million* paid out since 2010.”  (£300 million at the current exchange rate is equal to about CAD $500 million. ) 

What Scotland refers to as “constrained” Ontario calls “curtailed,” but they mean exactly the same thing. Ontario didn’t start constraining/curtailing generation until mid-September 2013, or almost three full years after the article’s reference date for Scotland. Curtailment prevents the grid from breaking down and causing blackout or brownouts.

The article from Energy Voice goes on: “In 2016 alone, Scottish onshore wind farms received £69million in constraint payments for limiting 1,048,890MWh worth of energy”.

Ontario in 2016, curtailed 2,327,228 MWh (megawatt hours). That figure comes from Scott Luft who uses data supplied by IESO (Independent Electricity System Operator) for grid-connected wind power projects and conservatively estimates curtailed wind for distributor-connected turbines to compile the information.

What that means: in 2016 it cost Ontario’s ratepayers CAD $$279.2 million** versus £69 million (CAD equivalent $115.2 million) for Scottish ratepayers. So, Ontario easily beat Scotland in both the amount of constrained wind generation as well as the subsidy cost for ratepayers who in both cases paid handsomely for the non-delivery of power!

The article went on to note: “By August 2017, the bill had already reached in excess of £55million in payments for 800,000MWh”!

Once again Ontario’s ratepayers easily took the subsidy title by curtailing 2.1 million MWh in the first eight months of the current year, coughing up over $252.5 million Canadian versus the equivalent of CAD $92 million by Scottish ratepayers.

In fact, since September 2013, Ontario has curtailed about 5.5 million MWh and ratepayers picked up subsidy costs of over $660 million.

Ratepayers in both Ontario and Scotland are victims of government mismanagement and wind power industry propaganda, and are paying to subsidize the intermittent and unreliable generation of electricity by industrial wind turbines.

(C) Parker Gallant

* One British Pound is currently equal to approximately CAD $1.67.

**Industrial wind generators are strongly rumored to be paid $120 per MWh for curtailed generation.

MOECC fails to act on wind turbine noise: CTV report

Turbines in K2 Wind power project were found to be out of compliance with Ontario regulations months ago. Since then, the Ministry of the Environment and Climate Change has done nothing, says a report by CTV News London.

http://london.ctvnews.ca/video?clipId=104066

September 13, 2017

Last spring, the MOECC determined that several industrial-scale wind turbines in the K2 Wind power development near Goderich, Ontario were operating out of compliance. This was the result of noise testing done by the Ministry, following numerous complaints by residents.

Former minister Glen Murray had promised action, saying there are rules to be followed, and his department would make sure they were.

Months later, nothing has been done. And residents continue to file reports of excessive noise and vibration daily.

In a report by Scott Miller of CTV London resident Mike Stachura says, “Nothing has changed…This is our home, we have to live here and we keep hoping the government will do something to help.”

Huron-Bruce MPP Lisa Thompson raised the issue in the Legislature Tuesday, asking new minister Chris Ballard when the Wynne government was going to take action to protect residents’ health. The minister responded with criticism of the Opposition, and reverted to the government’s green energy mantra.

 

Grey Highlands project cancelled: is Big Wind’s Gold Rush over?

Samsung Belle River project racing for completion: Ontario doesn’t need more wind power. Is the Gold Rush over?

Last week, Wind Works Power announced it has cancelled the Feed In Tariff (FIT) contract with the Independent Electricity System Operator for its Cloudy Ridge wind power project, to have been located in Grey Highlands.

The company, based in Germany, made this statement in its news release:

Given that the government of Ontario recently cancelled the previously repeatedly announced second bidding process for up to 850 MW renewable energy, and given the loss incurred by Cloudy Ridge due to repeated governmental uncertainties, Wind Works has decided to terminate any activities in the uncertain and unpredictable Ontario renewable energy market.

Wind Works also claimed that it had planned to “invest” $300 million in Ontario, but will not now due to cancellation of further wind power procurement and government “uncertainty.”

The Auditor General for Ontario has stated that Ontario has paid far too much for wind power and that in fact, the citizens of Ontario overpaid by as much as $9 billion.

A commentary published by the Council for Clean and Reliable Energy noted that Ontario has a surplus of power and that because wind power is produced out of phase with demand in the province, as much as 70 percent of wind power is unusable. Of the remained, little of it actually gets to areas in the GTA and southern Ontario where it is needed.

Wind Concerns Ontario received documents earlier this year indicating that the Ministry of the Environment and Climate Change has failed to address reports of excessive noise and vibration. The Ministry’s own staff documented concerns with existing regulations regarding noise levels and setbacks.

Five more wind power projects received contracts in 2016 and are now proceeding through the approval process.

“These projects are not needed,” says Wind Concerns Ontario president Jane Wilson. “If approved and allowed to proceed, they will add $3.3 billion in costs to Ontario electricity customers’ bills for intermittent and unreliable power that also has significant negative impact on the environment and human health.”

contact@windconcernsontario.ca

 

Ontario Environment Ministry set to repeat mistakes if new power projects approved

WIND CONCERNS ONTARIO

NEWS RELEASE

ONTARIO ENVIRONMENT MINISTRY TO REPEAT WIND POWER MISTAKES

August 22, 2017

Wellington, Ont. —

Applications for approval of new, huge wind power projects now being filed with the Ontario Ministry of the Environment and Climate should be denied, says Wind Concerns Ontario.

“There have been so many problems and mistakes with the government’s wind power program that not a single new project should be approved,” says Wind Concerns’ president Jane Wilson.

Recently, problems with well water have been revealed in the Chatham-Kent area, where vibrations from turbine construction and operation have disturbed the shale bedrock resulting in toxic heavy metals such as arsenic contaminating water, making it undrinkable.

On August 21st, Chatham-Kent council voted to demand a halt to construction of a new wind power project.

The Otter Creek project by French power developer Boralex is proposed to be built on the same geologic formation and there are questions as to whether it could also create water problems.

Turbine noise is an ongoing concern: Wind Concerns received MOECC documents earlier this year showing that the ministry has had thousands of complaints about excessive noise and vibration from operating wind turbines, but has not resolved any of the problems. Complaints about noise emissions from the turbines continue, often beginning as soon as the power projects begin operation. Citizens affected report sleep disturbance for weeks at a time, and other health problems such as headaches, dizziness, and cardiovascular symptoms.

“The Ministry doesn’t seem to be learning anything from reports of problems created by wind power projects,” says Wilson. “Their own field officers have documented issues with existing noise regulations and observed health effects, and now we have people with formerly pure well water turning black, but the MOECC continues to receive and approve these huge power projects based on the same regulations that have proven to be flawed.

“If the MOECC were a private business, they would acknowledge these mistakes and problems, and work to resolve them — that’s not what this government is doing.”

Wind Concerns filed a document recommending the Otter Creek project, now in review, not be approved. The turbines proposed have never been used and there are no actual noise output measurements for them, WCO says of the project which will operate immediately north of Wallaceburg.

“The modelling documents filed with their approval request are just estimates based on estimates,” says Wilson. “That’s not good enough to assure citizens of Wallaceburg their health will be protected.”

WCO says that projects not built yet should also be halted, such as the North Kent II, where water problems persist, and Amherst Island, to name two, where a tiny island community will be exposed to noise emissions from 26 50-storey high wind turbines and endangered wildlife will be affected.

The damage to the environment and to human health is inexcusable, WCO says, especially when the power projects are not needed. According to a report by the Council for Clean & Reliable Energy, 70 percent of Ontario’s wind power is wasted as it is produced out of phase with demand, and Ontario has a surplus of electrical power.

contact@windconcernsontario.ca

Wind Concerns Ontario comment to the MOECC on the Otter Creek project: CommentsOtterCreek-August18

Home in Huron County: thousands of noise complaints remain unresolved — yet government approving more projects? [Photo Gary Moon]
Turbines will cause devastation of Amherst Island heritage community, endanger wildlife — project should be cancelled, says WCO [Map: Wayne Gulden, Wind Farm Realities]

Modern day larceny: independent editor on Ontario’s wind power push

Rick Conroy, editor of the independent Wellington Times news paper in Prince Edward County, has had a front-row seat to at least three, probably four, wind power projects in The County. All have been vanquished save for the “White Pines” unwanted, unneeded power project which has been reduced from 29 turbines to 27 then to nine, and still, the power developer threatens to proceed.

Conroy has an interesting perspective, including a view across the water to nearby Amherst Island, where a tiny island community will almost certainly be destroyed by the Windlectric unwanted, unneeded wind power project … that will take a whole lot of wildlife down with the island, too.

Here is his editorial from the most recent edition of the paper.

No matter how you look at it, Ontario’s energy policy doesn’t make any sense

Ontario is currently working toward another electricity import deal with Quebec. It is likely a good thing. Most of our neighbour’s electricity is generated by massive hydro dams on the James Bay and St. Lawrence watershed—so, by today’s convoluted meaning of the word, it is clean. It is also reliable and manageable—the opposite of the wind and solar power sources in which Ontario has invested billions over the past 15 years. The deal is expensive, however, about 40 per cent richer than Quebec earns from other exported electricity contracts.

But here is the interesting bit.

Coincidentally, the quantity of imported power represented in this deal, combined with another with Quebec in 2015— equals almost precisely the total electricity generated by wind and solar in Ontario. Ten terawatt hours of wind and solar are being made redundant by ten terawatt hours of hydro electricity. Maybe coincidence is the wrong word.

Put another away—the nearly useless intermittent power generated by wind and solar has been replaced by two power deals with Quebec. Electricity that is cheaper, cleaner and manageable.

It’s a sign, perhaps, the adults have wrested control of the province’s energy management away from the politicians.

The deal illustrates rather bluntly that Ontario’s wind and solar power projects are like costume jewellery—showy and glittery to a distracted public, but bearing little actual value.

Worse, these intermittent electricity trinkets are a persistent headache to the electricity system operator. Each year we spill enough electricity through exports to neighbouring jurisdictions, including Michigan and New York, to power a large part of their economies. We regularly export this power at a loss—sometimes we pay them to take it.

Sickeningly we spend as much as a $1 billion each year for others to take our unwanted electricity. Without these outlets, however, Ontario’s power grid would succumb to the variability of wind and sunlight on an electrical grid ill-equipped to endure it. And electrical systems operators in Michigan and New York know it.

So, they take advantage.

It is sophisticated modernday larceny. Here is how it works. Lacking formal purchase agreements, Michigan buys Ontario electricity mostly on the spot market, typically paying between one and two cents per kilowatt hour (kWh)—a fraction of what it costs the state to generate its own electricity. (The County’s Parker Gallant does a much more thorough job of explaining how this works in his regular contributions to the Wind Concerns Ontario blog, the Financial Post and other publications.)

To its credit and downfall, Ontario’s electricity market is utterly transparent—anyone with a computer can monitor the demand for electricity and the supply available at any given moment (as well as many other facets of the system). They can see plainly when the province is headed for a critical system overload— when Ontario must shed power or risk catastrophe. Folks in Michigan know it too. They know when Ontario will be calling them to offload electricity. They are happy and ready to oblige.

From time to time, the imbalance between too little demand and too much uncontrollable supply in Ontario’s electricity system becomes so precarious that grid operators in Michigan and New York can actually compel Ontario to pay them to take it the power. It is how it came about that today Ontario now powers about 10 per cent of Michigan’s electricity needs. And we lose money on every kilowatt.

All this has been said and explained before by others. The facts are uncontested. It is all easily verifiable thanks to Ontario’s transparent electricity operations.

Yet we continue to build useless wind and solar projects. We continue to make the problem worse.

Across the channel from Cressy, Amherst Island residents are bracing for a disheartening defeat. Their local government has recently conceded that it has secured the most it is likely to get from the developer of 26 industrial wind turbines and the province in order to protect the residents, the delicate waterway, the roads and other infrastructure as well as the endangered species that reside there. Any lingering regret over its own shortcomings at Loyalist Township hall, however, is likely to be eased by the $500,000 payment it has been promised each year by the industrial wind project owner.

Meanwhile on the ground, the developer’s actions sometimes bear little resemblance to the plans it submitted and promises made when asking from provincial approvals. For example, it told the Environmental Review Tribunal that it would widen only about three kilometres of road. Now it figures it will need to widen more than six times that length—a threat to the Blanding’s turtles and other animals. It is also threatening to fundamentally change the character of this pastoral island for a generation or more.

Folks on Amherst Island have begun to mourn the looming decimation of the quiet, rural island life that drew them to this place. We mourn with them.

Michigan residents, meanwhile, are likely unaware of the sacrifices that some Ontario residents on a wee island are making to subsidize their electricity bills.Will we connect these dots next June?

 

rick@wellingtontimes.ca