Goulais bay appeal concludes; Ontario awaits ruling

The appeal of one of two wind power projects in Ontario’s Algoma region has concluded; a ruling may not come down for months.

Appeal completed; ruling could take months

By Elaine Della-Mattia, Sault Star

(QMI Agency file photo)
(QMI Agency file photo)
  • A decision into the appeal of the Goulais Wind Farm project may not be rendered until mid April.

An Environmental Review Tribunal heard arguments for more than two days earlier this week from opponents who don’t want to see a wind farm created in Goulais.
The appeal was filed by Heyden resident Doug Moseley with the assistance of Lake Superior Action Research Conservation (LSARC) and the law offices of Eric Gillespie. The appeal was also supported by the Save Our Algoma Region (SOAR) groups.
In October, it was announced that the Goulais Wind Farm project had been approved by the provincial government.
The decision, posted on the Ontario Environmental Registry, said the renewable energy approval has been issued to SP Development Limited Partnership to engage in a renewable energy project for a Class 4 wind facility that will have a total capacity of 25 MW.
The 11-wind turbine facility must be built and operational within three years.
But opponents argued that the industrial wind turbines are harmful to human health and disruptive and destructive to the natural environment and wildlife habitat.
They also argued that the wind turbines contribute to the rising cost of electricity and are totally unnecessary to produce clean energy in Ontario.
Involved parties will file their final written submissions to the tribunal by Jan. 20 and a decision on the appeal is expected to be made before April 22.

Read the full story here.