Save Ontario $500 million: cancel wind power contract, says community group

August 29, 2016
The Windlectric wind power project on tiny Amherst Island has no hope of meeting its “drop-dead” Commercial Operation date, so Ontario’s Independent Electricity System Operator (IESO) can cancel the Feed In Tariff (FIT) contract right now, with no penalty, says the Association to Protect Amherst Island.
See the letter to IESO Chair Tim O’Neill here and below.
header-12.jpg

Dear Dr. O’Neill,

In August 2015 The Association to Protect Amherst Island requested that the IESO exercise its ability to cancel the Fit Contract dated February 25, 2011 with Windlectric Inc. (Algonquin Power) without penalty because of the inability of the company to achieve its commercial operation date.

In its 2016 Q2 Quarterly Report, extract attached, Algonquin now advises that construction is expected to take 12 to 18 months and that the Commercial Operation Date will be in 2018. This timeline is contrary to what was submitted to the Environmental Review Tribunal and to the Ontario Energy Board. A COD of 2018 is seven years from the date of award of the contract.

Cancellation of the contract at this time would enable the IESO to achieve cost avoidance exceeding $500 million over the next 20 years based on the high cost of power generation at 13.5 cents per kilowatt-hour set out in the contract with Windlectric and based on the IESO’s commitment to pay Windlectric to not produce power when capacity exceeds demand. Cancellation of the Windlectric contract could be achieved without penalty due to noncompliance and would address in part the IESO’s budget challenges and energy poverty in Ontario.

Accordingly, the Association reiterates its request that IESO cancel the FIT Contract with Windlectric Inc.

Rick Conroy, in the attached article from the Wellington Times, explains the Kafkaesque and cruel nature of allowing the Amherst island project to continue especially in light of the unused power capacity of the nearby Lennox Generating Station and the Napanee Gas Plant under construction.

In summary:

Windlectric cannot comply with the Commercial Operation Date in its FIT Contract.

At a time of skyrocketing hydro rates and financial challenges the IESO could save $500 million over the next 20 years by cancelling the Windlectric Contract without penalty.

Existing nearby generating capacity is almost never used and will increase when the Napanee Gas Plant comes online. Intermittent and expensive power from wind turbines on Amherst Island is not necessary

Finally, please provide the IESO’s understanding of the Commercial Operation Date for Windlectric, any extensions awarded by the IESO, and the number of days granted due to Force Majeure and judicial matters.

Thank you for your consideration.

Sincerely,

Michèle Le Lay

President

Association to Protect Amherst Island

CC Premier Kathleen Wynne

Honourable Glenn Thibeault, Minister
 

What's your reaction?
0Cool0Upset0Love0Lol

3 Comments

  • Pat Cusack
    Posted August 29, 2016 10:16 am 0Likes

    Interesting to see this new GE plant being built in Welland will use engines presumably fired by natural gas or diesel to enable it to go off grid during peak periods. They are a major manufacturer of both wind turbine and solar components. Gives one a lot of faith in the future of wind and solar to provide our needs. Bernie

  • whooper
    Posted August 30, 2016 9:04 am 0Likes

    Hypocrites! If GE’s “green” renewable energy/ IWTs scheme is so noble, then GE should be required to reap the exorbitant hydro rates like the rest of us instead of going “off-grid” burning “dirty” oil, gas and diesel while they make a killing on the backs of ratepayers with this IWT scam!

  • Trackback: Energy & Environmental Newsletter: September 12, 2016 - Master Resource

Add Comment

© Copyright 2022 | WCO | Wind Concerns Ontario

to top